Villa Miami Reaches 37 of 56 Floors in Edgewater
The 70-residence Edgewater tower by Terra and One Thousand Group was two thirds of the way up in May 2026. Its first listings ask about three times what Edgewater condos have sold for.

Villa Miami, the 56-story condo tower rising at 710 NE 29th Street in Edgewater, had reached its 37th floor by May 12, 2026, according to Florida YIMBY's latest progress report. That is about two thirds of its final height, up from the 28th floor in March. The developers and the trade press both still target completion in late 2027. As of October 13, 2026, we found no public report that the tower has topped out.
Construction so far
| Date | Milestone | |---|---| | May 9, 2025 | Concrete foundation pour completed, four weeks ahead of schedule | | January 2026 | Vertical construction reaches 21 floors | | March 2026 | Superstructure at about the 28th of 56 floors | | May 2026 | Tower reaches the 37th floor | | Late 2027 | Scheduled completion |
Florida YIMBY and PROFILEmiami both reported the foundation pour, which Moss Construction carried out in a single 14-hour operation, and both covered the 21st-floor milestone in late January 2026. Florida YIMBY's aerial photos in March showed the structure at the halfway mark.
What is being built at 710 NE 29th Street
Villa Miami is a joint venture of Terra and One Thousand Group, with Major Food Group, the restaurant company behind Carbone, handling the dining and hospitality program. It is the restaurant group's first branded residential tower, PROFILEmiami reported. The plan in brief:
- Size: 650 feet, 56 stories, and only 70 residences, each a half floor or a full floor.
- Team: ODP Architects, Moss Construction as general contractor, and interiors by AD100 designer Vicky Charles.
- Amenities: The Copper Club, a three-level private amenity suite with dining rooms, lounges, a screening room, a salon and wellness space, plus a rooftop helipad. A waterfront restaurant at the base, run by Major Food Group, gives residents priority seating.
- The top: a three-story penthouse of roughly 15,000 square feet, unveiled in December 2025 at an asking price of $55 million.
The listings already on the market
The building is not finished, but it already has listings. On September 21, 2026, three units were for sale, with a median asking price of $5.85 million, or $2,034 per square foot, and a median HOA fee of $6,274 a month.
Compare that with the finished waterfront towers nearby, using closed sales over the past 12 months as of October 13, 2026:
- Elysee: 11 sales at a median $1,087 per square foot, against a median ask of $1,316.
- Aria Reserve: 37 sales at a median $997 per square foot.
- Missoni Baia: 20 sales at a median $986 per square foot.
- One Paraiso: 17 sales at a median $984 per square foot.
Older bayfront towers sit lower again: Biscayne Beach closed 24 sales at a median $847 per square foot, and Paraiso Bay 13 at $780.
Villa's price band is the thinnest part of the market. Our Edgewater market report counts 8 condos listed at $5 million and up, and no closed sale at that level in the last 12 months. Between $2 million and $5 million, 71 condos are listed against 43 sales, about 19.8 months of supply.
Across all of Edgewater, 490 condos sold in the last 12 months at a median of $605 per square foot. With 532 active listings, that is about 13 months of supply. Our Market Index for the neighborhood reads 35, which leans toward buyers.
Why it matters to buyers and owners nearby
A new-tower premium, not a neighborhood price. At about $2,000 per square foot, Villa Miami's listings ask roughly three times the Edgewater median sale and nearly twice the highest building median we track nearby, Elysee's $1,087 per square foot. Whatever price these units reach will say little about the value of an older unit nearby. The closest guide is the price at which Elysee and Missoni Baia units actually sell, not what they ask.
Nothing has closed yet. Villa Miami has no recorded closings or mortgages so far. Its first resale prices and financing terms will only appear in the county record after delivery, and a $5 million-plus resale in Edgewater currently has no recent closed sale to compare against.
The developer's record is measurable. Terra is the lead brand on 17 buildings we track, 13 of them scored. Its Developer Score is 71 (A minus), based on how its delivered buildings perform on quality, financial health, financing and the market.
Timing. Floor 37 in May puts topping out several months away, and the late-2027 target leaves time for facade, interior and certificate-of-occupancy work. Anyone buying under contract should read the contract's outside delivery date rather than rely on a marketing target.
Frequently asked questions
When will Villa Miami be completed?+
The developers and Florida YIMBY's construction reports target late 2027. In May 2026 the tower had reached its 37th of 56 floors; no topping out had been reported as of October 13, 2026.
How many residences does Villa Miami have?+
70 half-floor and full-floor residences in a 56-story, 650-foot tower at 710 NE 29th Street in Edgewater.
Sources
- Florida YIMBYMay 12, 202656-Story Villa Miami Continues Ascent At 710 NE 29th Street In Edgewater, Miamifloridayimby.com ↗
- Florida YIMBYMar 7, 2026Aerial Views Show Villa Miami's Superstructure Reaching Halfway Mark In Edgewaterfloridayimby.com ↗
- Florida YIMBYJan 30, 2026Villa Miami Reaches 21 Floors Above Biscayne Bay At 710 NE 29th Street In Edgewaterfloridayimby.com ↗
- Florida YIMBYMay 16, 2025Foundation Work Completed At Villa Miami, A 650-Foot Residential Tower Rising In Edgewaterfloridayimby.com ↗
- PROFILEmiamiJan 28, 2026Construction On Villa Miami Surpasses 21st Floorprofilemiami.com ↗
- PROFILEmiamiMay 27, 2025Villa Miami Completes Concrete Pour On Landmark Waterfront Tower In Edgewaterprofilemiami.com ↗
- PROFILEmiamiDec 8, 2025Villa Miami Reveals $55 Million, 15,000 SF Three-Story Estate In The Sky In Edgewaterprofilemiamire.com ↗
- Multi-Housing NewsMoss Construction to Build Luxury Miami Condo Towermultihousingnews.com ↗
More Edgewater news
Edgewater's New Condo Towers: What Delivers in 2026, 2027 and 2028
Edgewater has two towers closing now and about 812 condo units under construction for 2027 and 2028. Own.Miami deed and listing data show how that pipeline compares with what the neighborhood sells in a year.
Tower 36 Is Now Anantara Miami Resort & Residences
The Tower 36 plat filing of September 2025 led to a new plan: Anantara Miami Resort & Residences, a 50-story tower at 3601 Biscayne Boulevard with 100 branded condos, resort residences and hotel suites, slated for 2030.
Crescent Heights Plans 1,030 Live Local Apartments on Biscayne in Edgewater
Crescent Heights' two-tower Live Local Act project at Biscayne Boulevard and NE 32nd Street now plans 1,030 apartments, 412 of them workforce units, after a September 2026 design review.
Neo Edgewater Starts Leasing 399 Rentals at 2600 Biscayne Blvd
Oak Row Equities' 41-story 2600 Biscayne tower began preleasing its 399 Neo Edgewater apartments in September 2026, with one month free on 14- to 18-month leases.